Hot Water Everywhere
The challenge – ironic given the desert setting – was water.
The shaft that Cementation was hired to sink was essentially a proof-of-concept, designed to show that Resolution could get down underneath the ore deposit, build a network of lateral tunnels capable of withstanding the rock stresses and pressure, and extract the copper using a technique known as block cave mining. So getting to the bottom was priority No. 1. Any lateral tunnels, known as “drifts,” would have to wait.
From the start, everyone understood heat was going to be an issue. “The deeper the mine, the hotter the rock,” Seppala says. “So we knew that going down 7,000 feet, we’d have 180 degree rock temperature.”
The water was “the big surprise.”
“Test drilling indicated we could expect about 80 gallons a minute,” Seppala says. “We ended up getting close to 500 gallons a minute.”
The constant deluge of water – some of it as hot as the rock – created conditions that overwhelmed the first chiller system installed onsite and brought the shaft sinking to a standstill more than once.
Merely pumping freezing air into the mine wasn’t enough. So Denogean’s team installed a larger exhaust system to pull the heat out and added an additional chilling system halfway down the shaft to re-cool the air.
Like everything else on the project, the six, 13,000-pound chiller units had to be slung down the hole. “Underground has its own set of inherent challenges and logistics is just one them,” Denogean says. “You can’t just drive material to where it’s needed.”
Lifting lugs had to be engineered and weld on to the units and guides attached so they didn’t flop around in the shaft as they were lowered. And when they got to their destination, halfway down the open shaft, they had to be pulled in and installed on the tight inset.
Nothing was easy. Everything took much longer than it would topside. Equipment continually failed. “Nothing lasts down there as long as it would anywhere else,” Denogean says. “Not gear. Not electronics. Not monitoring devices. Nothing. You got the heat, you’ve got the water, you’re even dealing with a change in barometric pressure. So if we need something, we buy three or four of them. One’s not going to do it. One won’t last. “
Even with the additional chillers, conditions are “adverse,” Denogean says. Arizonans don’t deny their state gets hot. But they insist it's more bearable than, say, South Florida in the summertime because "it's a dry heat.”
That may be the case in Phoenix and Tucson. But at the bottom of Ten Shaft, as the 7,000 feet hole Cementation built here was officially known, things are a lot stickier.
Down here, the ambient air temperature after cooling ranged between 85 and 90 degrees Fahrenheit all day and night and the humidity never, ever drops below 100 percent.
It's essentially South Florida. In the summertime. On steroids. Hell on both men and machines.